Services & Requests

New Services Queue - filterable view of generation interconnection queues, merchant transmission queues, long-term firm transmission service requests, Auction Revenue Rights analyses and queues under construction/in service
New Service Requests
Planning Modeling Submissions (MOD-032)
Generation Deactivations

Interconnection Study Statistics PDF 
Incremental Auction Revenue Rights Model Development & Analysis PDF

Public Policy Requirements

The State Agreement Approach detailed in the PJM Operating Agreement, Schedule 6, section 1.5.9  WEB | PDF provides a mechanism whereby a state or group of states can submit a public policy project to PJM to address state-specific public policy requirements, so long as the state(s) agrees to pay all costs associated with the state-selected build-out included in the Regional Transmission Expansion Plan.

New Jersey Board of Public Utilities Order 

On Nov. 18, 2020, the New Jersey Board of Public Utilities (NJBPU) notified PJM of an Offshore Wind Transmission Order PDF specifying its public policy requirements for offshore wind. The order requested that PJM open a competitive proposal window in 2021 to solicit onshore and offshore project proposals that address New Jersey’s public policy needs.

Point of Interconnection & Associated Injected Amounts 

Location State Transmission Owner MFO MW Energy MW Capacity Notification Date Requested In-Service Date 
Deans 500 kV NJ PSEG 3,100 3,100 930 11.18.2020 2028–2035
Smithburg 500 kV NJ JCPL 1,200 1,200 360 11.18.2020 2028–2035
Larrabee 230 kV NJ JCPL 1,200 1,200 360 11.18.2020 2028–2035
Cardiff 230 kV NJ AEC 900 900 270 11.18.2020 2028–2035